Our works are progressing well. Next week we will be carrying out; Continuation of roof joisting Installing rebar into the rib deck and pouring the concrete Continuation of 2nd floor joisting Continuation of 1st floor steel work Continuation of front lightwell underpinning Removal of existing temp works where possible Reducing mass to internal of basement Continuation of underpinning 2nd stage internally Temp works continuation to front vault